Tasks

Bulk out for 2 Houses and Garages

Detail excavation

Footings

Drilled Piers

Client

Complex Homes

Status
  • Completed
Start

11 March 2019

End

21 march 2019

Budget

$

Complex Homes

We recently performed bulk excavation of 1300T to accommodate for a set of detached duplexes, which was loaded into Trucks and removed from site. 

We then detailed the pad, dig footings to support retaining walls and drilled piers to support the house.

While we were there we also dug the trenchers for B & D Plumbing.

Project Brief

Excavation to accommodate for detached duplexes. The bulk and detailed excavation was completed in 9 days.

  • Detached duplexes.
  • 2 Double Garages for each house.
  • 1 Will have an in-ground pool.